8-Phase Land

Subdivision Process

Phase 7

Click to see details

Phase 7 - Final Map and Site Improvement Plans Approval

This phase includes receiving and responding to the various municipality agencies comments on the Final Map and Site Improvement Plans. Upon issuance of all of the Site Improvement Permits, the Property Owner can begin the construction of the project’s infrastructure.

 
You will now need to pay all the required development fees.  These fees can be substantial.  When the construction is complete and all of the fees are paid, the Planning Department will release the Final Map for final signatures, approval and recordation with the local County.

Phase 7 - Final Map and Site Improvement Plans Approval

This phase includes receiving and responding to the various municipality agencies comments on the Final Map and Site Improvement Plans. Upon issuance of all of the Site Improvement Permits, the Property Owner can begin the construction of the project’s infrastructure.

 
You will now need to pay all the required development fees.  These fees can be substantial.  When the construction is complete and all of the fees are paid, the Planning Department will release the Final Map for final signatures, approval and recordation with the local County.

Phase 7 - Final Map and Site Improvement Plans Approval

This phase includes receiving and responding to the various municipality agencies comments on the Final Map and Site Improvement Plans. Upon issuance of all of the Site Improvement Permits, the Property Owner can begin the construction of the project’s infrastructure.

 
You will now need to pay all the required development fees.  These fees can be substantial.  When the construction is complete and all of the fees are paid, the Planning Department will release the Final Map for final signatures, approval and recordation with the local County.

Municipality Comments by Planning, Building, Fire, Etc.

Upon submittal, the Final Map is reviewed by your Municipality’s Land Surveying Department. The Site Improvement Plans are reviewed by several municipality departments and utility agencies, such as the Planning, Building, Fire and etc.  Upon completion of each agency’s review, it is typical that each agency will have a series of comments that will need to be addressed before final approvals are granted.

 The Site Improvement Plans are reviewed by several municipality departments and utility agencies, such as the Planning, Building, Fire and etc. departments.  Upon completion of each agency’s review, it is typical that each agency will have a series of comments that will need to be addressed before final approvals are granted.

Municipality Comments by Planning, Building, Fire, Etc.

Upon submittal, the Final Map is reviewed by your Municipality’s Land Surveying Department. The Site Improvement Plans are reviewed by several municipality departments and utility agencies, such as the Planning, Building, Fire and etc.  Upon completion of each agency’s review, it is typical that each agency will have a series of comments that will need to be addressed before final approvals are granted.

 The Site Improvement Plans are reviewed by several municipality departments and utility agencies, such as the Planning, Building, Fire and etc. departments.  Upon completion of each agency’s review, it is typical that each agency will have a series of comments that will need to be addressed before final approvals are granted.

Municipality Comments by Planning, Building, Fire, Etc.

Upon submittal, the Final Map is reviewed by your Municipality’s Land Surveying Department. The Site Improvement Plans are reviewed by several municipality departments and utility agencies, such as the Planning, Building, Fire and etc.  Upon completion of each agency’s review, it is typical that each agency will have a series of comments that will need to be addressed before final approvals are granted.

 The Site Improvement Plans are reviewed by several municipality departments and utility agencies, such as the Planning, Building, Fire and etc. departments.  Upon completion of each agency’s review, it is typical that each agency will have a series of comments that will need to be addressed before final approvals are granted.

Revise Plans per Comments

The local municipality typically has technical comments regarding the various design documents submitted as part of the approval process. You’re required to modify the drawings accordingly and resubmit them to the municipality for review and approval.

Revise Plans per Comments

The local municipality typically has technical comments regarding the various design documents submitted as part of the approval process. You’re required to modify the drawings accordingly and resubmit them to the municipality for review and approval.

Revise Plans per Comments

The local municipality typically has technical comments regarding the various design documents submitted as part of the approval process. You’re required to modify the drawings accordingly and resubmit them to the municipality for review and approval.

Technical Drawings are Complete

Revised plans are accepted.  All drawings have been submitted and approved.  All technical documents are complete.

Technical Drawings are Complete

Revised plans are accepted.  All drawings have been submitted and approved.  All technical documents are complete.

Technical Drawings are Complete

Revised plans are accepted.  All drawings have been submitted and approved.  All technical documents are complete.

End of Contract

With the completion of the Final Map and Site Improvement Plans Approval, the contract for Phase 7 is complete.

End of Contract

With the completion of the Final Map and Site Improvement Plans Approval, the contract for Phase 7 is complete.

End of Contract

With the completion of the Final Map and Site Improvement Plans Approval, the contract for Phase 7 is complete.

Phase 8

Developer Tasks, Record Final Map


GoTo Phase 8

Phase 8

Developer Tasks, Record Final Map


GoTo Phase 8

Phase 8

Developer Tasks, Record Final Map


GoTo Phase 8

An additional contract will be required for Phase 8

Comments and revisions may cause delays and/or additional costs

An additional contract will be required for Phase 8

Comments and revisions may cause delays and/or additional costs

Phase 7 Steps

  • Phase 7 Final Map and Site Improvement Plans Approval

    This phase includes receiving and responding to the various municipality agencies comments on the Final Map and Site Improvement Plans. Upon issuance of all of the Site Improvement Permits, the Property Owner can begin the construction of the project’s infrastructure. 

     You will now need to pay all the required development fees.  These fees can be substantial.  When the construction is complete and all of the fees are paid, the Planning Department will release the Final Map for final signatures, approval and recordation with the local County.

  • Municipality Comments by Planning, Building, Fire, Etc.

    Upon submittal, the Final Map is reviewed by your Municipality’s Land Surveying Department. The Site Improvement Plans are reviewed by several municipality departments and utility agencies, such as the Planning, Building, Fire and etc.  Upon completion of each agency’s review, it is typical that each agency will have a series of comments that will need to be addressed before final approvals are granted.

     The Site Improvement Plans are reviewed by several municipality departments and utility agencies, such as the Planning, Building, Fire and etc. departments.  Upon completion of each agency’s review, it is typical that each agency will have a series of comments that will need to be addressed before final approvals are granted.

  • Revise Plans per Comments

    The local municipality typically has technical comments regarding the various design documents submitted as part of the approval process. You’re required to modify the drawings accordingly and resubmit them to the municipality for review and approval.

  • Technical Drawings are Complete

    Revised plans are accepted.  All drawings have been submitted and approved.  All technical documents are complete.

  • End of Contract

    With the completion of the Final Map and Site Improvement Plans Approval, the contract for Phase 7 is complete. 

  • Phase 8

    Developer Tasks, Record Final Map


    GO TO PHRASE 8

Share by: