  The design and development of a project is a complex process. We use the following 8-phase process:

  • Phase 1 – Research and Budget
  • Phase 2 – Initial “Go” “No-Go” Decision
  • Phase 3 – Preliminary Design
  • Phase 4 – Land Use (Entitlement) Approval (Refer to separate flowchart)*
  • Phase 5 – Final “Go” “No-Go” Decision
  • Phase 6 – Construction Documents
  • Phase 7 – Building Permits
  • Phase 8 – Construction Administration

* Take special note of Phase 4. This phase is extremely complicated by itself. We have provided a separate flowchart to illustrate its complexity